We have successfully completed R. Kinolhas Shore protection project. Scope of works include, 19,780cbm reclamation operations and construction of a 650m geo bag revetment.
MTCC has signed an agreement with the Ministry of Transport and Civil Aviation to implement Phase 1 of the “Malé Taxi Line” initiative. The project aims to introduce
The F. Magoodhoo Airport Development Project is currently underway, with runway ABC works reaching 56% completion and the Terminal Building works at 53% completion. Additionally,
The final shipment of quay wall blocks for the HA. Uligan Harbor Development & Shore Protection Project has been delivered to the site. Unloading and installation work is
N. Lhohi Harbor Development Project is well underway. Construction of quay wall and installation of concrete blocks for the construction of quay wall are currently ongoing,
Th. Guraidhoo Land Reclamation and Shore Protection Project for the development of Th. Guraidhoo Airport is well underway. We have commenced construction of bund wall at the
Ha. Uligan Harbor Development and Shore Protection Project is well underway. Second shipment of concrete blocks required for quay wall construction have been delivered to the
The N. Kudafari Shore Protection Project is currently underway with 57% project progress. Geobag filling works are progressing at 35%, while the installation of Geobag works
The installation of a third barrier island for the HA. Hoarafushi Shore Protection Project is currently underway with 70% project progress. Additionally, geobag installation
The Ha. Thuraakunu Mosque Development Project is currently underway. Concrete works for both male and female ablution areas have been complete, and shuttering and bar bending
Sh. Komandoo Shore Protection work is progressing well, with 100% completion of the revetment curb stone works. Additionally, we have received approval for the Komandoo Harbor
Ha. Muraidhoo Harbor Development Project is well underway, with overall 92% project progress. Rock boulders required for the remaining project works have been delivered to the
The Madaveli-Hoadehdhoo Causeway Project is currently underway. The first 60m bridge has reached 85% completion, and the second 60m bridge has reached 80% completion. Approach
In the past year, the B. Eydhafushi Harbor Development Project has seen remarkable progress. Dredging for the existing harbor is 94% complete, dredging for the harbor channel
B. Eydhafushi Harbor Development Project is well underway. Channel dredging and existing harbor dredging operations are ongoing, with 97% and 87% completion respectively. In
Ha. Dhihdhoo Harbor Extension and Jetty Construction Project is well underway, with overall 87% project progress. Breakwater profiling and revetment profiling works are currently
N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is well underway, with overall 93% project progress. Construction of a jetty at south side of the harbor
Th. Kinbidhoo Land Reclamation Project is well underway. Reclamation operations are ongoing, with 30% completion.
Ga. Villingili Harbor Development Project (Phase 3) is well underway, with overall 52% project progress. Installation of anchor blocks for quay wall construction and harbor
R. Kinolhas Shore Protection Project is well underway, with overall 76% project progress. Reclamation and compaction operations are currently ongoing, with 75% completion. Scope
The AA. Feridhoo Harbor Development Project is currently ongoing. Quay wall block installation work has been completed, and new harbor basin dredging work has reached 91% completion.
Ha. Muraidhoo Harbor Development Project is well underway, with overall 90% project progress. We have completed breakwater profiling works. Scope of works include, 28,175cbm
Sh. Maaungoodhoo Harbor Development Project is currently underway with 70% project completion. The second shipment of rock boulders has been delivered to the project site, and