M. Muli Harbor Development Project is well underway

M. Muli Harbor Development Project is well underway. We have completed installation of concrete blocks required for quay wall construction. Construction of breakwater, pavement works and quay wall concrete works are ongoing at site.
The scope of the project includes, harbor basin dredging operations of 33,888cbm, channel dredging operations of 6,254cbm, construction of a 465m breakwater, 89m revetment, 479m quay wall, 3m wide bridge, and installation of 2,730sqm harbor pavement, navigational and harbor lights. The value of the project is MVR 61.8 million.