Work on S. Hulhudhoo Harbour is well underway

Work on S. Hulhudhoo Harbour is well underway, with overall 23% project progress. Dredging works for the project is currently ongoing.
The S. Hulhudhoo Harbour project consists of; dredging and excavation operations of 88,623cbm; construction of a 114m breakwater; a 624m revetment; a 742m quay wall; 2,250 sqm of paved area and installation of streetlights. The estimated value of the project is MVR 65.1 million. The project was awarded on 01 March 2020.