05 Apr The extension of the existing harbour for Sh. Komandoo harbour upgrade project is well underway
The extension of the existing harbour for Sh. Komandoo harbour upgrade project is well underway. Current work involves quay wall works and dredging and reclamation of the harbour basin.
The Sh. Komandoo project consists of dredging and excavation operations; along with construction of a 12m long breakwater; revetment works; and a 190m quay wall.
31% of the project is now complete.