Completion of Phase Two of the harbor construction project in Kelaa

We have successfully completed Phase Two of the harbor construction project in Kelaa, Haa Alif Atoll on 9th July 2020.
HA. Kelaa harbor construction Phase Two consists of 3,496 cubic meters of maintenance dredging; 12,768 cubic meters of channel dredging; a 30 meter breakwater; a 220 meter revetment, a 50 meter quay wall and 1,445 square meter of paved area. Navigation lights, two harbour lights and mooring buoys were also installed on the harbor, under the scheme.
The Ministry of National Planning, Housing and Infrastructure contracted the MVR 17.4 million project to us on June 30, 2019. The project was subsequently mobilized on 13th September 2019.

 