Work on B. Fehendhoo Harbour is well underway, with overall 43% project progress

Work on B. Fehendhoo Harbour is well underway, with overall 43% project progress. Channel dredging works for the project are currently ongoing, with 76% completion. We also completed 80% of harbour basin works needed for the project.
The B. Fehendhoo harbour project consists of channel dredging of 25,000 cbm; harbour basin dredging of 18,500 cbm; construction of a 130mb breakwater; a 282m revetment; a 214m quay wall; paved area; navigation lights and a bridge.
The estimated value of the project is MVR 49.6 million. The project was awarded to us on 2nd July 2019 with subsequent mobilization undertaken on 10th November 2019.