19 Jul Work on B. Fehendhoo Harbour is well underway, with overall 43% project progress
Work on B. Fehendhoo Harbour is well underway, with overall 43% project progress. Channel dredging works for the project are currently ongoing, with 76% completion. We also completed 80% of harbour basin works needed for the project.
The B. Fehendhoo harbour project consists of channel dredging of 25,000 cbm; harbour basin dredging of 18,500 cbm; construction of a 130mb breakwater; a 282m revetment; a 214m quay wall; paved area; navigation lights and a bridge.