26 Dec Work on Design and Build of B. Fehendhoo Harbour is well underway
Work on Design and Build of B. Fehendhoo Harbour is well underway, with overall 62% project progress. Quay wall concrete works for the project is currently ongoing, with 40% completion.
Scope of works for the project include new harbor basin dredging operations of 18,500cbm; new entrance channel dredging operations of 25,000cbm; the construction of a 214m quay wall; a 130m breakwater; and a 282m revetment. Additionally, the installation of navigation lights, installation of streetlights and installation of 558sqm of paved area will also be undertaken. The estimated value of the project is MVR 45.1 million. The project was mobilized on 10th November 2019.
Sorry, the comment form is closed at this time.