We have mobilized Adh. Omadhoo Harbor Development Project site

We have mobilized Adh. Omadhoo Harbor Development Project site on 30th July 2023.
Scope of works include, 49,765cbm dredging and excavation operations, 12,105cbm channel dredging operations, construction of a 346m quay wall; a 398m breakwater; a 208m revetment; installation of 1,6470sqm harbor pavement, construction of a ramp, construction of concrete jetty (150m x 2m), installation of harbor lights and navigational lights. The value of the project is MVR 66.96 million.