09 Apr We have completed 84% reclamation of the first island and 75% reclamation for the second island of Centara Three Islands Reclamation project
‪We have completed 84% reclamation of the first island and 75% reclamation for the second island of Centara Three Islands Reclamation project.
The construction of a groyne and revetment to mitigate the effects of erosion are ongoing for the first island.