Road construction project of R. Ungoofaaru is well underway

Road construction project of R. Ungoofaaru is well underway. The asphalt plant has been mobilized to the project site. Our plan is to commence paving during December 2020.
Scope of work involve a carriageway of 16,488 sqm, sidewalks, stormwater management system, road lighting and road markings. The road development project was contracted to us by Ministry of National Planning, Housing and Infrastructure and was mobilized on 12th June 2019. The project is valued at MVR. 30.3 million.