Gdh. Faresmaathoda Airport Development Project has reached overall 82% project progress

Gdh. Faresmaathoda Airport Development Project is currently underway, with overall 82% project progress. Fire building and terminal building construction works have reached 95% and 80% completion respectively, and installation works for the boundary and security fence are currently ongoing at the site.

The scope of the project includes, subbase and subgrade works for runway, taxiway, apron, fire pad and fire road, construction of a fire building and a terminal building.