The construction of Gn. Fuvahmulah Ring Road Project is nearing completion

The construction of Gn. Fuvahmulah Ring Road Project is nearing completion, with overall 83% project progress. Currently installation of concrete paving blocks is ongoing, with 41% completion. We have scheduled to complete the project during November 2020.
Scope of works involve construction and development of 20,650sqm asphalt road with natural infiltration system; installation of 144 LED streetlights; speed breakers and road markings. The road development project was contracted to us by Ministry of National Planning, Housing and Infrastructure and was mobilized on 29th March 2020. The project is valued at MVR. 32.04 million.