Road construction project of R. Ungoofaaru is well underway

Road construction project of R. Ungoofaaru is well underway, with overall 85% project progress. We have completed subgrade works of the carriageway. Laying of Aggregate Base Course (ABC layer) is currently ongoing, with 95% completion.
Scope of work involve construction of 16,488sqm asphalt roads, ABC works on an area of 16,488sqm, subgrade works on an area of 16488sqm and establishment of a stormwater management system. The value of the project is MVR 28.02 million.