Breakwater profiling works of AA. Maalhos Harbor Development Project is currently ongoing at 61% completion.

Breakwater profiling works of AA. Maalhos Harbor Development Project is currently ongoing at 61% completion. We have already completed the dredging operations during March 2022. Overall project progress is now at 45% completion.
Scope of works involve, dredging and excavation operations of 24,335cbm, construction of a 394m quay wall, a 407m breakwater, a 100m revetment, a 56m groyne, installation of 1970sqm harbor pavement, construction of a ramp and installation of harbor lights. The value of the project is MVR 56.9 million.
No Comments

Sorry, the comment form is closed at this time.