Work on B. Kamadhoo Harbor Development Project is well underway

Work on B. Kamadhoo Harbor Development Project is well underway, with overall 54% project progress. Third shipment of rock boulders have been delivered to the project site.
Scope of works include, 30,933cbm of dredging operations, 5,085 cbm of channel dredging operations, construction of a 181m breakwater; a 656m revetment; a 392m quay wall, installation of 1,670 sqm harbor pavement, construction of a ramp, and installation of navigational lights and harbor lights. The value of the project is MVR 48.63 million.