22 Aug 2021 - 14:53 We have completed the construction of breakwater of N. Miladhoo Harbor
Posted at 14:53h
in
News
by admin
We have completed the construction of breakwater of N. Miladhoo Harbor today. The construction of revetment is currently ongoing, with 56% completion. Our target is to complete the project before the end of this year.
The N. Miladhoo Harbour project consists of; dredging and excavation operations of 37,222cbm; construction of a 248m breakwater; a 137m revetment; a 286m quay wall; 1,430sqm of paved area; installation of navigation lights and streetlights. The value of the project is MVR 42.1 million.
×