Work on M. Veyvah Harbour is well underway

Work on M. Veyvah Harbour is well underway, with overall 39% project progress. The construction of a concrete wall and the installation of mooring rings are currently ongoing, with 39% and 20% completion respectively.
The M. Veyvah Harbour project consists of; dredging and excavation operations of 60,839cbm; construction of a 350m breakwater; a 35m revetment; a 380m quay wall; 1,880sqm of paved area and installation of street lights. The estimated value of the project is MVR 48.8 million. The project was awarded on 27th August 2019.