06 May The airport construction phase of work for HA. Hoarafushi airport development project is now underway
The airport construction phase of work for HA. Hoarafushi airport development project is now underway.
Currently, an asphalt plant and accessories have been transferred to HA. Hoarafushi. Asphalt plant installation and testing works will be carried out during this month and we plan to start asphalt works in June.
Airport construction work involves construction of a 1200 m runway; 8,635 sqm of apron and taxiway; service roads at air & land side in front of terminal; 9,473 sqm of parking area; 1,718 sqm of fire access road and a 720 m of airport security and beach fence area.
842,200 cbm of dredging and reclamation needed for the project was completed on 30th August 2019. A 1,120 m revetment, also needed for the project, was completed on 2nd March 2020.
Overall, our scope of the airport project will be completed before 18th September 2020, and the project is scheduled to achieve the targeted date.
The project, which was awarded to us on 25th March 2019, was subsequently mobilized on 18th April 2019.
Sorry, the comment form is closed at this time.