Lh. Hinnavaru Harbor Development Project is currently underway with overall 90% project progress.

Work on Lh. Hinnavaru Harbor Development Project is currently underway with overall 90% project progress. Harbor excavation and sheet piling works have been completed, and panel installation work is currently ongoing at the site.

Scope of works for the project include, reclamation operations of 3.2 hectare; dredging operations of 65,170.76cbm; construction of a 421m quay wall; a 123.9m breakwater; a 170.55m revetment. The value of the project is MVR 99.52 million.
#MTCCProjects #RayyithungeKunfuni