12 Jun 2022 - 15:38 Fuvahmulah City Internal Roads Construction Project is well underway with overall 72.65% project progress.
Posted at 15:38h
in
News
by admin
Fuvahmulah City Internal Roads Construction Project is well underway with overall 72.65% project progress. Stormwater Drainage works are currently ongoing at site.
Scope of works for the project include sub base preparation of 122,659sqm; an asphalt wearing course of 95, 239 sqm; footpath preparation of 27,450sqm; road marking, streetlights, and storm water drainage works of 19,940m. The value of the project is MVR 331.05 million.
×