Work on Hdh. Nellaidhoo Harbour is Well Underway

Work on Hdh. Nellaidhoo Harbour is well underway, with overall 30% project progress. Harbour dredging work is currently ongoing with 45% completion.

The Hdh. Nellaidhoo harbor development scheme consist of harbor basin dredging operations of 22,860cbm, maintenance dredging operations of 10,294cbm, breakwater construction of 164m, groynes construction of 125m, and quay wall construction of 224m.

It also involves installation of 2,102sqm of paved area, installation of navigation lights and streetlights and ramp construction. The estimated value of the project is MVR 47,623,290.28. The project was awarded to us on 27th August 2019.