The construction of major roads for L. Fonadhoo is well underway

The construction of major roads for L. Fonadhoo is well underway, with overall 64% project progress. Currently, subbase laying works on an area of 5200sqm is ongoing.
The project will see the development of 12 major roads with a total length of 3.5 km. Project works also involve construction of 27,848sqm asphalt roads, stormwater management system, speed breakers and road markings. The road development project was contracted to us by Ministry of National Planning, Housing and Infrastructure and was mobilized on 26th June 2019. The project is valued at MVR. 25.5 million.