The Harbour Upgrade Work of Sh. Komandoo is well underway

The Harbour Upgrade Work of Sh. Komandoo is well underway, with overall 73% project progress. The installation of quay wall blocks is now complete, and concreting work is ongoing on the insitu wall & capping beam of quay wall structures.

Additionally, project works include maintenance of new harbour hasin dredging of 35, 348cbm; channel dredging of 14,371cbm; breakwater construction of 12m; revetment construction of 20m; quay wall construction of 190m; installation of 1,991 sqm pavement & installation of navigation lights and street lights. The estimated value of the project is MVR 29.41 million. The project was mobilized on 8th December 2019.

No Comments

Sorry, the comment form is closed at this time.