We have mobilized Hdh. Kunribi Harbor Development Project site

We have mobilized Hdh. Kunribi Harbor Development Project site on 4th June 2023.
Scope of works involve, new harbor basin dredging operations of 30,172 cbm, existing harbour basin dredging operations of 4,389 cbm, existing harbour entrance channel dredging operations of 2,040 cbm, construction of a 295m breakwater; a 70m revetment; a 314m quay wall, construction of a ramp (10m x 9m), construction of an access platform, paving works (1,556.61 sqm) and Harbour light installation. The value of the project is MVR 40.56 million.