29 Jun Work is well underway for design and build of HA. Kelaa Harbour Phase Two
Work is well underway for design and build of HA. Kelaa Harbour Phase Two; with completion of channel dredging works, maintenance dredging and installation of mooring buoys. Work on revetment construction is currently ongoing.
The scheme for this project involves maintenance dredging operations of 3,496cbm; channel dredging of 12, 768cbm; along with construction of a 30m breakwater; a 220m revetment; a 50m quay wall and 1,445sqm paved area. The scheme also includes mooring buoys and streetlights installation.