Work is full swing for design and build of M. Veyvah harbor project with 3.5m concrete quay wall T-units needed for quay wall works transferred to the project site

Work is full swing for design and build of M. Veyvah harbor project with 3.5m concrete quay wall T-units needed for quay wall works transferred to the project site on 22nd June 2020. Currently, our team is preparing for quay wall installation.
Dredging operations of 56,925cbm from the new harbour basin was completed on 18th June 2020. The project also involves construction of a 380m quay wall; 350m breakwater; and a 130m revetment and the installation of streetlights and mooring blocks.
Overalls scope of works for the MVR 48.8 million project is expected to be completed ‪in 500 days‬. The project was awarded on 27th August 2019.