Gdh. Gahdhoo Harbor Development Project is currently underway with 57% overall project completion.

Gdh. Gahdhoo Harbor Development Project is currently underway with 57% overall project completion. Quay wall block installation work has been completed, and quay wall concrete work is currently ongoing at the site.

Scope of works include, dredging and excavation operations of 23,017cbm, construction of a 232m breakwater, a 35m revetment, a 320m quay wall, construction of a 320m Scouring Apron, a bridge, installation of 1600sqm harbor pavement and harbor lights. The value of the project is MVR 40.2 million.
#MTCCProjects #RayyithungeKunfuni