Under the Construction of Major Roads at R. Dhuvaafaru (2nd phase), asphalt works are progressing with 75% completion. Pavement works are ongoing with 91% completion.

Under the Construction of Major Roads at R. Dhuvaafaru (2nd phase), asphalt works are progressing with 75% completion. Pavement works are ongoing with 91% completion. Street lights required for the project has been delivered to the project site.
Scope of works involve, construction of 9 roads with a total length of 17,790sqm; sidewalks of 6,923sqm; a carriageway of 17,790sqm; installation of stormwater management system, road lighting and road markings. The project is valued at MVR 37.8 million.