The first shipment of rock boulders required for the breakwater construction of Sh. Bilehfahi Harbor have been delivered to the project site

The first shipment of rock boulders required for the breakwater construction of Sh. Bilehfahi Harbor have been delivered to the project site on 28th September 2021.
Scope of works involve, dredging and excavation operations of 24,125cbm; construction of a 376m breakwater; a 98m quay wall; installation of 1,150 sqm paved area and installation of streetlights. The value of the project is MVR 28.42 million