08 Feb Work on design and build of Sh. Bilehfahi Harbor Development Project is well underway
Work on design and build of Sh. Bilehfahi Harbor Development Project is well underway, with overall 72% project progress. Second shipment of rock boulders required for breakwater construction have been delivered to the project site. Breakwater profiling works are currently ongoing.
The scope of the project includes, dredging operations of 50,376cbm, construction of a 181m quay wall, a 170m revetment, a 434m breakwater, installation of 1565sqm pavement, installation of navigation lights and streetlights. The value of the project is MVR 28.42 million.