24 Jun The construction and development of major roads in L. Fonadhoo is well underway
The construction and development of major roads in L. Fonadhoo is well underway, with 56% project progress. Under this project, 27, 848 sqm area of asphalt will be laid along 12 roads which have a total length of 3.5 km.
The road construction project includes a storm water management system which will help to mitigate floods for the islands, in addition to protecting property. The project also involves construction of speed breakers and road markings of 13,702m.
Overall, the project is expected to be completed within 390 days. The project, which was awarded to us on 22nd May 2019, was subsequently mobilized on 26th June 2019.