Work on design and build of L. Maavah Harbor is well underway

Work on design and build of L. Maavah Harbor is well underway, with overall 72% project progress. Construction of Breakwater for the project is currently ongoing, with 57% completion.
The L. Maavah Harbour project consists of; dredging and excavation operations of 26,885cbm; construction of a 284m breakwater; a 40m revetment; a 110m quay wall and installation of 550sqm of paved area. The value of the project is MVR 27.3 million. The project was mobilized on 07th April 2020.