We have successfully completed the S. Maradhoo Harbor Breakwater Reconstruction Project

We have successfully completed the S. Maradhoo Harbor Breakwater Reconstruction Project on 29 November 2020. Scope of works for the project include dredging operations of 18,873cbm; the construction of a 419m quay wall; a 340m revetment; a bridge measuring 40m length x 6m width and installation of 1,975 sqm of paved area
The Ministry of National Planning, Housing and Infrastructure contracted the MVR 28.2 million project to us on 30 June 2019. The project was mobilized on 03 November 2019.