24 Jun Work is well underway for design and build of R. Madduvari South Harbor
Work is well underway for design and build of R. Madduvari South Harbor; with 90% of harbor basin dredging and 95% of channel dredging complete.
The scheme for this project involves dredging operations of 72,800cbm; along with construction of a 411m breakwater; a 135m revetment; a 566m quay wall and 2,825sqm paved area. The scheme also includes navigation and streetlights installation.