03 Jun The installation of pre-casted quay wall blocks for N. Henbadhoo harbour upgrade is well underway, with 60% overall project progress
The installation of pre-casted quay wall blocks for N. Henbadhoo harbour upgrade is well underway, with 60% overall project progress.
Pre-casted blocks from our Thilafushi site were transferred to N. Henbadhoo to construct a 203m quay wall. Overall, the N. Henbadhoo harbour upgrade consists of dredging and excavation operations of 44,615cbm along with construction of a 259m breakwater, a 173m revetment; 25m new groynes, and a 203m quay wall.