Work on Design and Build of M. Veyvah Harbour is well underway

Work on Design and Build of M. Veyvah Harbour is well underway. Topping slab casting caping works is currently ongoing, with 79% completion.
The M. Veyvah Harbour project consists of; new harbor basin dredging operations of 56,925cbm; existing harbor basin dredging operations of 5,992cbm; construction of a 350m breakwater; a 130m revetment; installation of 1,880sqm of paved area and installation of streetlights.