06 Sep Work on Ha. Hoarafushi Football Ground Sub Base Preparation project is well underway
Work on Ha. Hoarafushi Football Ground Sub Base Preparation project is well underway, with overall 61% project progress. Kerb stone laying, casting of drainage gutter top, subbase fill leveling and compaction works are currently ongoing.
Additionally, project works include site clearing and compaction of 8,103sqm and excavating the required area. It also involves installing a soak pit. The MVR 2.53 million project was awarded to us by the Ministry of Youth, Sports & Community Empowerment on 11th September 2019.