Work on Dh. Hulhudheli Harbour is well underway

Work on Dh. Hulhudheli Harbour is well underway, with overall 20% project progress. Dredging of the new harbour basin for the project is currently ongoing, with 26% completion.
The Dh. Hulhudheli Harbour project consists of dredging and excavation operations of 45,585cbm; construction of a 277m breakwater; a 60m revetment; a 432m quay wall; 2,160sqm of paved area and installation of streetlights. The estimated value of the project is MVR 39.8 million. The project was mobilized on 25th June 2020.