02 Sep Work on Dh. Hulhudheli Harbour is well underway
Work on Dh. Hulhudheli Harbour is well underway, with overall 20% project progress. Dredging of the new harbour basin for the project is currently ongoing, with 26% completion.
The Dh. Hulhudheli Harbour project consists of dredging and excavation operations of 45,585cbm; construction of a 277m breakwater; a 60m revetment; a 432m quay wall; 2,160sqm of paved area and installation of streetlights. The estimated value of the project is MVR 39.8 million. The project was mobilized on 25th June 2020.
Sorry, the comment form is closed at this time.