Work on Design and Build of B. Fulhadhoo Harbour is well underway

Work on Design and Build of B. Fulhadhoo Harbour is well underway, with overall 50% project progress. Dredging works for the project is currently ongoing, with 87% completion.
Scope of works for the project include dredging 29,167.50cbm from channel; dredging 22,694cbm from harbor basin; the construction of a 223m quay wall; a 108m breakwater; and a 302m revetment. Additionally, the installation of 558sqm of paved area, installation of navigation lights and streetlights will also be undertaken. The value of the project is MVR 48.2 million. The project was mobilized on 10th November 2019.