CEO Adam Azim & Minister of State for National Planning, Housing & Infrastruture Akram Kamaludheen inspected the progress of Ha. Hoarafushi airport project

CEO Adam Azim & Minister of State for National Planning, Housing & Infrastruture Akram Kamaludheen inspected the progress of Ha. Hoarafushi airport project on 22 October 2020. We are working around the clock to complete the project before 8th November 2020.

Airport construction work involves construction of a 1200 m runway, 8,635m² of apron and taxiway, service roads at air and land side in front of terminal, 9,473m² of parking area, 1,718m² of fire access road and a 720m of airport security and beach fence area, passenger terminal and fire building. 842,200 cubic meters of dredging and reclamation project work was completed in August 2019. A 1,120 meters of revetment was also completed in March 2020.

During this visit Media was also briefed on the latest updates of the project.

 