14 Aug Work on design and build of Sh. Lhaimagu Harbor Development Project is well underway
Posted at 15:41h
in
News
by Samahath Zuhuree
Work on design and build of Sh. Lhaimagu Harbor Development Project is well underway, with overall 54% project progress. Installation of precast concrete blocks for quay wall construction is ongoing, with 70% completion.
Sh. Lhaimagu Harbour project consists of; dredging and excavation operations of 31,000cbm; construction of a 350m breakwater; a 276m quay wall; a 500m revetment; installation of 1,380sqm pavement, installation of navigation lights and streetlights. The value of the project is MVR 56.3 million.