New harbor basin dredging works for the Sh. Lhaimagu Harbor development project is currently ongoing

New harbor basin dredging works for the Sh. Lhaimagu Harbor development project is currently ongoing, with 78% completion. The first shipment of rock boulders required for breakwater construction have been delivered to the project site on 13th March 2021.
The Sh. Lhaimagu Harbour project consists of; dredging and excavation operations of 31,000cbm; construction of a 350m breakwater; a 276m quay wall; a 500m revetment; installation of 1,380sqm pavement, installation of navigation lights and streetlights. The value of the project is MVR 56.3 million.