N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is well underway، with overall 55% project progress. We have completed channel breakwater operations and construction of ramp.
Scope of works for the project include; dredging and excavation operations of 29,038cbm; construction of a 195m breakwater; a 188m revetment; a concrete bridge; a ramp, and installation of navigational aids. The value of the project is MVR 30.3 million.