We have successfully completed Design and Build of V. Rakeedhoo Harbour project on 30th March 2021.

We have successfully completed Design and Build of V. Rakeedhoo Harbour project on 30th March 2021.
Scope of works for the project include dredging and excavation operations of 5,654cbm; boat beaching area dredging operations of 11306cbm; the construction of a 198m quay wall; the construction of a 156m breakwater; a 44m revetment, the installation of 594sqm of harbor pavements. The value of the project is MVR 18.5 million.