Work on the design and build of R. Angolhitheem Harbor is well underway

Work on the design and build of R. Angolhitheem Harbor is well underway, with overall 53% project progress. We have completed installation of harbor pavement.
The R. Angolhitheem Harbour project consists of; dredging and excavation operations of 42,615 cbm; construction of a 221m breakwater; a 166m revetment; a 91m quay wall; installation of 1110sqm paved area, installation of harbor lights and navigation lights. The value of the project is MVR 40.7 million