Work on Design and Build of Hdh. Nellaidhoo Harbour is well underway

Work on Design and Build of Hdh. Nellaidhoo Harbour is well underway, with overall 42% project progress. Installation of precast concrete blocks required for quay wall construction is currently ongoing, with 53% completion.
The Hdh. Nellaidhoo harbor development scheme consists of dredging and reclamation operations of 62,863cbm, breakwater construction of 331m, quay wall construction of 204m, revetment construction of 50m, installation of 2,102sqm paved area, installation of navigation lights and streetlights. The value of the project is MVR 47.62 million. The project was mobilized on 27th February 2020.