Work on Design and Build of L. Isdhoo Harbour is underway

Work on Design and Build of L. Isdhoo Harbour is underway, with overall 12% project progress. Dredging works for the project is currently ongoing, with 26% completion.
Scope of works for the project include dredging and excavation operations of 27,129cbm; the construction of a 230m quay wall; a 208m breakwater; 98m revetment, and 1,560sqm of paved area. The estimated value of the project is MVR 34.7 million. The project was awarded on 18th December 2019.