S. Hulhudhoo Football Ground Sub Base Preparation project is nearing completion, with overall 90% project progress.

S. Hulhudhoo Football Ground Sub Base Preparation project is nearing completion, with overall 90% project progress. Kerb stone laying and pipe installation needed for the project are now complete. Casting of drainage gutter top and pavement block installation are currently ongoing.

Additionally, project works include site clearing and compaction of 8,103sqm and excavating the required area. It also involves installing a soak pit. The MVR 2.49 million project was awarded to us by the Ministry of Youth, Sports & Community Empowerment on 11th September 2019.