16 Jul Rock boulders needed for shore protection component of K. Maafushi Land Reclamation and Shore Protection project have been delivered to the project site
Rock boulders needed for shore protection component of K. Maafushi Land Reclamation and Shore Protection project have been delivered to the project site. 25 hectares of land reclamation needed for the project was completed on 14th June 2020. Overall project progress is 66%.