28 Oct Work on Hdh. Hanimaadhoo Harbour is well underway
Work on Hdh. Hanimaadhoo Harbour is well underway, with overall 25% project progress. Harbor Basin Dredging works for the project is currently ongoing, with 53% completion.
The Hdh. Hanimaadhoo Harbour project consists of; harbour basin dredging of 53,523cbm; maintenance dredging of 31,576cbm; construction of a 355m breakwater; a 50m revetment; a 270m quay wall; 2,583sqm of paved area and installation of navigation lights. The value of the project is MVR 57.12 million. The project was mobilized on 05 May 2020.
Sorry, the comment form is closed at this time.